|
452 S.E.2d 188
215 Ga.App. 669
Court of Appeals of Georgia.
Dec. 2, 1994.
Reconsideration Denied Dec. 16, 1994.
Certiorari Denied March 17, 1995.
Awtrey & Parker, M. David Harrison, J. Ben Moore, Marietta,
for appellant.
David J. Farnham, Atlanta, for appellees.
SMITH, Judge.
This is an appeal from an order vacating an arbitration award
under the somewhat novel provisions of the Georgia Arbitration
Code, OCGA § 9-9-1 et seq. Paradoxically, appellant is
the party that sought to have the award vacated and, conversely,
appellees are the parties who defended the award as rendered.
Moreover, the court's judgment is deemed final for appeal
purposes even though it is undisputed the case must be returned
to the arbitrator for rehearing. OCGA § 9-9-13(e).
Appellees Brad and Rita Cross sought arbitration against
appellant Amerispec Franchise (Amerispec) for consequential
damages resulting from the negligent inspection of a home
ultimately purchased by the Crosses. The inspection agreement
drafted by Amerispec provides, in pertinent part, that claims
based on it or the resulting inspection report "shall
be resolved exclusively by arbitration in compliance with
the rules of the American Arbitration Association.... The
arbitration decision shall be binding on all parties."
The agreement also contains a "limit of liability"
clause essentially providing that "our liability to you
is limited to the fee paid for our inspection services and
you release us from any additional liability." The fee
paid was $150.
The arbitrator, however, awarded the Crosses $25,888, with
interest after thirty days to accrue at eight percent annually
until paid. Amerispec then applied to the superior court to
vacate the award. OCGA § 9-9-13. The superior court vacated
the award and ordered a rehearing, but only on the issue of
the rate of interest established by the arbitrator. Because
its order vacating the arbitrator's award did not grant the
entire relief requested, Amerispec appeals from the judgment
of the superior court. See OCGA §§ 9-9-16, 9-9-13(e).
See also Walton Acoustics v. Currahee Constr. Co., 197 Ga.App.
659, 660, 399 S.E.2d 265 (1990), overruled on other grounds,
Hope & Assoc. v. [215 Ga.App. 670] Marvin M. Black Co.,
205 Ga.App. 561, 562(1), 422 S.E.2d 918 (1992) (court may
vacate arbitration award only in its entirety); Mid-American
Elevator Co. v. Gemco Elevator Co., 189 Ga.App. 143, 145(1),
375 S.E.2d 275 (1988) (although statute mandates that entire
award must be vacated, court may limit rehearing to specific
issues necessitating that action).
"The function of the trial court in proceedings to confirm
or vacate an arbitration award should be severely limited
in order not to frustrate the purpose of avoiding litigation
by resorting to arbitration." Cotton States Mut. Ins.
Co. v. Nunnally Lumber Co., 176
Ga.App. 232, 236-237(4), 335 S.E.2d 708 (1985). OCGA §
9-9-13(b) reflects this policy, providing that an arbitration
award may be vacated due to such fundamental procedural defects
as corruption, fraud, misconduct, partiality, overstepping
of the arbitrator's authority (addressing issues not properly
before the arbitrator), or imperfect execution of that authority
(significant failure to fully and clearly address the issues
presented). As for questions purely of substance, OCGA §
9-9-13(d) makes clear "[t]he fact that the relief was
such that it could not or would not be granted by a court
of law or equity is not ground for vacating or refusing to
confirm the award."
1. In two enumerations of error, Amerispec argues that to
justify an award in excess of the amount of the fee originally
paid by the Crosses, the arbitrator either erred in his interpretation
of the agreement or in allowing the Crosses to rescind the
inspection agreement and sue for fraud in the inducement.
The superior court found the award reflects that the limitation
of liability clause was deemed void by the arbitrator. The
superior court also found no evidence that the arbitrator
"overstepped his authority" within the meaning of
OCGA § 9-9-13(b)(3).
"The dispute between the parties involved the meaning,
interpretation and application of certain terms of the contract
and these were matters for the [arbitrator] to determine.
The [arbitrator] having resolved the dispute in favor of appellee[s],
the trial court considered the record of the arbitration proceedings
and determined that neither the contract terms nor the applicable
law had been ignored by the [arbitrator]. Our review of the
record reveals no error in the trial court's ruling."
(Citations omitted.) City of College Park v. Batson-Cook Co.,
196 Ga.App. 138, 140, 395 S.E.2d 385 (1990).
Specifically, the parties indicate the arbitrator most likely
applied OCGA § 13-8-2(b) to their agreement, which renders
unenforceable exculpatory clauses in agreements "relative
to the construction, alteration, repair, or maintenance of
a building structure, appurtenances, and appliances."
The case now before us does not present squarely the question
of whether exculpatory clauses in home inspection agreements
are enforceable in light of OCGA § 13-8-2(b); [215 Ga.App.
671] instead, the question in this case is whether the arbitrator's
determination on the matter is not only in error, but so clearly
erroneous that it implicates the very integrity of the arbitrator
in the exercise of his authority. OCGA § 9-9-13(b).
This limitation on our inquiry follows from the general rule
that "an arbitrator's decision must be upheld unless
it is completely irrational or it constitutes a manifest disregard
of the law." Bartlett v. Dimension Designs, 195 Ga.App.
845, 848, 395 S.E.2d 64 (1990), overruled on other grounds,
Pace Constr. Corp. v. Northpark Assoc., 215 Ga.App. 438, 450
S.E.2d 828 (1994). The applicability of OCGA § 13-8-2(b)
to limitation of liability clauses in home inspection agreements
had not been addressed in a reported decision at the time
the award was made. Moreover, OCGA § 13-8-2(b) does not
represent a model of legislative clarity. Consequently, we
agree with the superior court that voiding the limitation
of liability clause does not compel an inference that the
arbitrator overstepped his authority. We therefore find no
error in the superior court's order vacating the arbitration
award but limiting rehearing to the question of the proper
interest rate to be applied after 30 days if the award remains
unpaid. Mid-American Elevator Co. v. Gemco Elevator Co., 183
Ga.App. 88, 89, 357 S.E.2d 838 (1987).
2. Amerispec's remaining enumerations, to the extent not
addressed in Division 1, are without merit.
Judgment affirmed.
POPE, C.J., and McMURRAY, P.J., concur.
*
Note: The text of this opinion is public record
|